So what's going on?


It may not appear, since we received our planning permission, that much has been happening on the project, but we can assure you that there's been plenty of action behind the scenes as well as activity around the site!

  • Detailed specifications have gone out to Tender to a selection of contractors.

  • A new electricity meter box has been constructed for the Multisport's supply.

  • The old hall floor has been lifted and removed.

  • UK Power Networks have been instructed to disconnect the electricity supply.

  • A local company has been selected to carry out demolition.

  • Fencing repaired.

  • Trees have been surveyed.

How the hall's interior looks now with no flooring...


Once we get the go ahead to knock the old building down you will start to see progress on site slowly initially over the coming month, but come springtime we hope to see the new hall start to go up!